After a three day delay due to weather, the work resumed on the remodel of barn two today. The trusses were added to the addition. So now it is easier to visualize the final result. The foundation was started for the wash rack as well. The remainder of the metal will be ordered tomorrow, and if the materials arrive by Friday morning and the weather holds off, the outside of the remodel could be completed by weeks end.