Bittersweet Acres Farm

Week Two of Barn Remodel Complete

by on Apr.24, 2010, under Uncategorized

Twins with handprintshandprintsThe workers were consistent this week. The wall for the front of the barn was framedElliot edging concreteEntranceJimmy working concreteand the remainder of the windows put in. The rest of the metal was put on the barn and the remainder of the doors were framed. The concrete was poured for the entrance with the children’s handprints put in the entryway. The project was slightly delayed by weather and we are waiting for the trusses (they are suppose to be delivered on Monday). If all the material is delivered on time, the outside of the remodel will be completed next week.

No comments for this entry yet...

Leave a Reply

You must be logged in to post a comment.

Looking for something?

Use the form below to search the site:

Still not finding what you're looking for? Drop a comment on a post or contact us so we can take care of it!

Visit our friends!

A few highly recommended friends...