by Patrick on Apr.24, 2010, under Uncategorized
The workers were consistent this week. The wall for the front of the barn was framed
and the remainder of the windows put in. The rest of the metal was put on the barn and the remainder of the doors were framed. The concrete was poured for the entrance with the children’s handprints put in the entryway. The project was slightly delayed by weather and we are waiting for the trusses (they are suppose to be delivered on Monday). If all the material is delivered on time, the outside of the remodel will be completed next week.